New video from the concrete foundations of Trilogy’s East Tower

12/11/2019 14:57

The concrete foundations of Trilogy’s East Tower have been poured just one month after the West Tower’s.

East Tower Concrete Foundations in numbers:

  • 20 hours
  • 130 workers
  • 2,500m3 of concrete
  • 700 tonnes of reinforcement
  • 8 layers

Work on the second phase of construction is also in progress, including underground parking and the construction of the North Tower.